What an emergency action plan must include under 1926.35

The construction rule for an emergency action plan (EAP), 29 CFR 1926.35, is short: six elements the plan must cover, an alarm system, people trained to help with evacuation, and a review with the crew it covers. It sets no drill schedule, so a drill frequency credited to OSHA is someone else's number.

The six elements 1926.35 requires

  • Escape procedures and escape route assignments
  • Procedures for workers who stay behind to run critical operations before they evacuate
  • A way to account for every employee after the evacuation is finished
  • Rescue and medical duties for the workers assigned to perform them
  • The preferred way to report fires and other emergencies
  • Names or regular job titles of the people or departments to contact for more about the plan

Plan, alarm, evacuation

The cards run from what the written plan must contain to the calls a supervisor makes while the site empties.

Card 1 of 6 · 0 right

Card 1

A site uses the same single air-horn blast to signal a crane lift, a shift change, and an evacuation. Under 29 CFR 1926.35, what must the supervisor correct?

Pick an answer. A short note for each option, A to D, appears here.

Card 2

A project's emergency action plan was reviewed with all workers at mobilization. Six weeks later the assembly area is moved to make room for a crane pad. Under 29 CFR 1926.35, what is required?

Pick an answer. A short note for each option, A to D, appears here.

Card 3

After an evacuation alarm, crews gather at the assembly area. The sign-in roster shows 62 workers on site, but the superintendent counts only 60. What should the superintendent do FIRST?

Pick an answer. A short note for each option, A to D, appears here.

Card 4

During a real fire, the supervisor finds that the electric evacuation alarm is dead because its circuit tripped. What should the supervisor do FIRST?

Pick an answer. A short note for each option, A to D, appears here.

Card 5

During an evacuation, smoke from the fire drifts over the site's primary assembly area. What should the supervisor do?

Pick an answer. A short note for each option, A to D, appears here.

Card 6

A crew includes several workers with limited reading ability in any language. What is the MOST effective way to teach them the site's evacuation routes?

Pick an answer. A short note for each option, A to D, appears here.

    Two plans that get swapped

    Emergency action plan vs HAZWOPER emergency response plan
    PointEmergency action planHAZWOPER emergency response plan
    Rule29 CFR 1926.3529 CFR 1926.65(q)
    Written forEvery worker who has to get out and be countedWorkers who respond to a hazardous substance release
    Core jobEvacuate, account for everyone, reportRespond to the release itself
    Who actsEveryone, by leaving and being countedTrained responders, by containing the release

    HAZWOPER is the hazardous waste operations and emergency response standard. A small, incidental release that the crew in the area can absorb is not emergency response, and a worker trained only to the awareness level recognizes a release and notifies others.

    Details that decide the answer

    Small employers may skip the paper. With 10 or fewer employees, the plan may be communicated orally instead of written down. Ten is also the small-employer cutoff in OSHA recordkeeping (1904.1), a separate rule.

    The alarm system has to meet 29 CFR 1926.159 and give a distinctive signal for each purpose. Before the plan takes effect, the employer picks and trains enough people to help others out in a safe, orderly evacuation.

    The plan is reviewed with each covered worker when it is first developed, whenever that worker's responsibilities or designated actions under it change, and whenever the plan itself changes. Each worker also goes over the parts of the plan they need to know on initial assignment (29 CFR 1926.35(e)). The text is on osha.gov, 29 CFR 1926.35.

    For alarms, drills and evacuation as a whole, see the emergency action plans, alarms and drills sheet. Posting emergency numbers and the site's location is a first-aid rule, covered on first aid, rescue and severe weather.

    Drills, paperwork and the assembly area

    How often do construction crews have to run evacuation drills?

    29 CFR 1926.35 sets no frequency. Drill schedules come from company policy, the owner's contract or a consensus standard. Holding one at start-up and whenever the site layout or phase of work changes, with a headcount and a debrief, is good practice.

    Is the EAP the same thing as the site-specific safety plan?

    No. The EAP is required by 1926.35 and limited to emergencies. A site-specific safety plan is an industry practice covering the whole project, and it often carries the EAP as one section.

    Where should the assembly area go?

    The standard does not fix a spot. Good practice puts it clear of collapse and traffic zones, and upwind and uphill wherever a chemical release is possible.