Sheet 16Domain 3 of 5 · Health Hazards and Basic Industrial Hygiene

Heat and cold stress: signs, controls and STSC practice

No federal standard sets heat or cold limits for construction work as of October 2026. OSHA handles heat stress on construction sites through the General Duty Clause and a heat National Emphasis Program, and the practical rules come from OSHA and NIOSH guidance. This sheet sorts out which guidance stands behind which answer, and the cards put it to work on roofs, decks and trenches in both seasons.

What governs heat and cold on a jobsite

Where the rule behind each heat or cold answer comes from
TopicSource of the ruleWhere it trips people up
Heat illness preventionGeneral Duty Clause, Section 5(a)(1) of the OSH Act, plus OSHA's National Emphasis Program on heatHunting for a numeric limit when the duty is a general one
A federal heat standardProposed by OSHA in 2024; not a final rule as of October 2026Treating the proposal's trigger temperatures as law
Water, rest and shadeOSHA heat guidanceReading guidance amounts as legal minimums
AcclimatizationNIOSH recommendationsAssuming a fit, experienced worker needs no ramp-up
Cold stressOSHA and NIOSH cold-stress guidance; no construction standard of its ownTreating every cold injury the same way

OSHA's heat rulemaking page tracks the proposal. If you test well after October 2026, check it for a change in status.

Heat and cold cards

Summer roofs and closed-up floors, winter pours and wet trenches: the scenes run across both seasons, from the first sign of trouble to a medical emergency.

Card 1 of 15 · 0 right

Card 1

A drywall hanger on an unventilated upper floor in August reports headache, nausea and dizziness and is sweating heavily, but is alert and answering questions clearly. What should the supervisor do?

Pick an answer. A short note for each option, A to D, appears here.

Card 2

During a winter pour, a finisher who has been wet for hours is shivering violently, fumbling tools and slurring words. What should the supervisor do FIRST?

Pick an answer. A short note for each option, A to D, appears here.

Card 3

Pipe layers stood in water in a trench for several days in 40°F weather. Their feet are now red, swollen, tingling and numb, with no frozen tissue. Which condition is MOST likely?

Pick an answer. A short note for each option, A to D, appears here.

Card 4

A new laborer joins a roofing crew during a heat wave. Under NIOSH acclimatization guidance, how much of a full shift's heat exposure should this worker have on day 1?

Pick an answer. A short note for each option, A to D, appears here.

Card 5

A laborer is found confused and stumbling on a hot slab while still sweating heavily. The supervisor has called 911. What should be done NEXT while waiting for EMS?

Pick an answer. A short note for each option, A to D, appears here.

Card 6

Which of the following is a sign that a construction worker may be experiencing frostbite?

Pick an answer. A short note for each option, A to D, appears here.

Card 7

At the end of a hot week, a laborer reports muscle pain, unusual weakness and dark, cola-colored urine. What should the supervisor suspect?

Pick an answer. A short note for each option, A to D, appears here.

Card 8

Why does OSHA heat guidance recommend a buddy system for crews working in hot conditions?

Pick an answer. A short note for each option, A to D, appears here.

Card 9

Which returning or current worker should the supervisor treat as UNACCLIMATIZED and put on a gradual heat-exposure schedule?

Pick an answer. A short note for each option, A to D, appears here.

Card 10

An asbestos-abatement crew wears impermeable disposable coveralls and respirators in an un-air-conditioned building on an 88°F day. What should the supervisor recognize about their heat risk?

Pick an answer. A short note for each option, A to D, appears here.

Card 11

Which sign MOST clearly indicates that a worker's heat illness has progressed to heat stroke?

Pick an answer. A short note for each option, A to D, appears here.

Card 12

Which heat-stress control for an outdoor crew is an ENGINEERING control?

Pick an answer. A short note for each option, A to D, appears here.

Card 13

According to OSHA's heat illness prevention guidance, how much water should workers doing moderate work in the heat drink?

Pick an answer. A short note for each option, A to D, appears here.

Card 14

Which measurement BEST reflects the combined heat stress from air temperature, humidity, radiant heat from the sun, and air movement?

Pick an answer. A short note for each option, A to D, appears here.

Card 15

Before winter bridge work begins, a supervisor trains the crew on cold stress. Below what core body temperature is a worker considered to have hypothermia?

Pick an answer. A short note for each option, A to D, appears here.

    What the scene adds to the thermometer

    The forecast high is only part of the heat load. A sunlit roof, a fresh asphalt mat, the cab of an old loader with no air conditioning, a heavy task scheduled for mid-afternoon: each raises it without changing the number on your weather app. Cold works the same way through wind and wet clothing.

    Heat and cold terms worth knowing

    Heat rash
    Clusters of small, itchy red bumps where sweat stays on the skin, often under a harness or at the collar. A sign the crew is sweating hard.
    Heat cramps
    Painful muscle spasms during or after heavy sweating, when the body has lost salt along with water.
    Heat syncope
    Fainting or light-headedness, typically after standing still a long time or getting up fast in the heat.
    Wind chill
    How cold exposed skin feels once wind is added. A breezy 35°F bridge deck can be harder on a crew than a still day several degrees colder.
    General Duty Clause
    Section 5(a)(1) of the OSH Act: employers must keep the workplace free of recognized hazards likely to cause death or serious harm. OSHA uses it for heat cases because no heat standard exists.
    National Emphasis Program
    An OSHA enforcement plan that points inspections at one hazard. The heat program sends inspectors to high-heat industries on hot days.

    A heat and cold plan for one site

    • Someone checks the forecast each morning and adjusts the day's schedule
    • Cool drinking water within a short walk of every crew, refilled during the shift
    • A shaded or cooled rest area set up before the hot season starts
    • A written ramp-up schedule for workers new to the heat, following NIOSH acclimatization guidance
    • Heavy tasks moved to cooler hours on high-heat days
    • Warm, dry break space and spare dry gloves and socks on cold jobs
    • Every worker trained to spot heat and cold illness, with the site address ready for a 911 call

    Where this sheet sits in Domain 3

    Heat and cold share Domain 3, Health Hazards and Basic Industrial Hygiene, with two other sheets: ergonomics, vibration and noise and silica, lead and chemical exposures. BCSP weights the whole domain at 17.8% of the exam (STSC7 blueprint, as of October 2026), and the free STSC practice test draws on all five domains at once.